METHOD STATEMENT FOR PIPE JACKING WORK
INTRODUCTION
1.1 Introduction
The Vung Ang II thermal
power plant is part of the Vung Ang thermal power center and is the second
complex of the coal-fired electricity generating plant located in the Vung Ang
industrial zone, Ky Loi commune, Ky Anh district, Ha Tinh province in Vietnam.
Vung Ang II will be constructed adjacent to Vung Ang I which is already in
operation. It consists of two turbines with a total capacity of 1,200 MW. Both
will be fueled by imported anthracite, hard coal.
1.2 Abbreviation and definition
The Owner
Vung Ang II Thermal Power LLC
The Contractor DHI-SCT Joint Venture
HSE Health, Safety and
Environment
MS Method Statement
RA Risk Assessment
PPE Personal
Protective Equipment
QA/QC Quality
Assurance/Quality Control
1.3 Scope of work
To install the CW
underground pipeline of Vung Ang 2 Thermal Power Plant at crossing area with
Vung Ang 1 belt conveyor by pipe jacking pressing method.
1.3.1 Constructing of 04 CW pipelines with Diameter
2700mm
Number of CW pipelines
can be changed with 2 pipelines (DN 3700) at the detail engineering stage
2 OVERVIEW
CW pipe DN2700 to install
underground by Pipe jacking method.
Plan View of Construction Location
Table 1.1 Contents of
work
No |
Items |
Method statement |
Quantities |
Note |
A |
S |
|
|
|
1 |
Driving and extract
steel sheet pipe Larsen IV |
Use Silent
Piler(100-150T) |
|
|
2 |
Soil improvement for
bottom of shaft |
Jet Grouting D1800 |
2shaft |
|
3 |
Soil improvement for
entrance of launching and arriving shaft |
Jet Grouting D1200 |
|
|
4 |
Strut installation |
Lifting and installing |
|
|
5 |
Soil Excavation |
Use excavator |
|
|
B |
Pipe
jacking construction |
|
|
|
1 |
Supply DN2700 pipe |
|
|
|
2 |
Installation CW pipe
DN2700 |
Pipe Jacking |
40m |
|
Learn more METHOD STATEMENT FOR PIPE JACKING WORK >>